Lakeshore Drive Interceptor Project

This project will be installing an interceptor sewer line at the intersection of Lakeshore Drive by Colcord’s Point and going down Lakeshore Drive to Alexander Street.  This sewer line will be installed with a trenchless method.  Bolton and Menk are the engineers on the project and information on the project can be found at the following Link Lakeshore Drive Project

Notice To Bidders Center Lake Phase 2 Sewer Project

This project is for the installation of gravity sewer on the south end of Center Lake in Dickinson County, Iowa.  The project will contain both guided directional boring methods and open trench installation of C900 pipe.  This project is to allow for several properties in this area to be able to connect to the public sewer system and remove septic systems that are creating water quality issues in Center Lake and secondary issues for West Okoboji Lake.  The notice to bidders can be found at the link below.

Center Lake Sanitary Sewer Improvements Phase 2 Notice to Bidders

Two Major Project Completed

The Iowa Great Lakes Sanitary District has completed two major projects in the lakes area.  Phase 1 of the Center Lake Project included installing over 17,000 feet of sewer pipe and the relocation of the Hayward Bay Lift Station.  This work has closed some roads and limited access on others in Okoboji (Lakeshore Drive, Center Lake Road, Alexander Street and Nature Center Road)  and on County Roads (Nature Center Road, 220th Avenue and 165th Street) for the  last year.  The road surfaces are all installed and open for through traffic again.

New Hayward Bay Lift Station
New Road Completed at Intersection of Nature Center Road and Lakeshore Drive
New Road Completed at Lakeshore Drive and Center Lake Road

The Phase 1 of the Center Lake Project has relocated the Haywards Bay Lift Station out of the floodplain of West Okoboji, created capacity within the Sanitary District system from the City of Okoboji North and will allow for the public sewer to be expanded to the properties on the south side of Center Lake.  The extension of the public sewer to the properties of Center Lake is to protect the water quality of Center Lake, by providing public sewer to allow for the removal of septic systems along 165th Street, 231st Avenue and 225th Place.  The Sanitary District worked in cooperation with the City of Okoboji. Dickinson County Engineers Office, the Dickinson County Board of Supervisors and Dickinson County Conservation Board.  The Sanitary District appreciates the public’s patience during this project.

The other project that has been completed was in the City of Arnolds Park in two areas.  The first on Rohr Street in the area of Oar’s Campground and the second on Linden Drive in the area of Bridges Bay Resort.  This project changed the public sewer pipes in this area to create more capacity for future growth along the east side of East Okoboji and Big Spirit Lake.  Both Rohr Street and Liden Drive were closed for a few weeks during construction and to allow the concrete to cure.  Both Rohr Street and Linden Drive have been reopened for through traffic.  The Sanitary District worked in cooperation with the City of Arnolds Park on this project.  The Sanitary District again appreciates the public’s patience during this project.

New part of the Road on Rohr Street
Road Repair on Linden Drive

Up Coming Project Road Closures

The Sanitary District is continuing to make improvement to the public sewer system around the Iowa Great Lakes.  There are going to be some up coming road closure that will take place over the next couple of months that the District wants to make people aware of before the roads are shut down.

The first one is the final step of the new Haywards Bay lift station project.  This project will be closing down all of Alexander Street, a portion of Lakeshore Drive and a portion of Center Lake Road.  The map below shows the closure area.

The next area is on Linden Drive east of the City of Arnolds Park going towards Bridges Bay.  The detour for this road will direct traffic to the stop light on Broadway Street and then to Rohr Street and around back to Linden.  This will be a full road closure from Triggs Resort to past Bridges Bay Resort.  The map below details the road closure area.

The last road closure will be after Linden Drive is fully restored and will be on Rohr Street.  This full road closure that will start near Fehrway Drive and to Sandy Lane.  The map below details the area of the road closure.

Solar Project at Waste Water Treatment Plant

The first solar panels are going on to the racking as of 9/16/2020.  This is the first of eight rows that will be going up.

First solar panels going up on the racking at the Waste Water Treatment Plant. (9/16/2020)

 

 

 

 

 

 

 

 

 

 

 

The Solar Project at the Iowa Great Lakes Sanitary District Waste Water Treatment Plant started Construction on Tuesday September 8, 2020.  The project will continue over the next several weeks.  The Solar Project will provide up to 0.5 megawatt of power to off set cost power cost for the Wastewater Treatment Plant.  The pay back is estimated to be about 7 years.

The wastewater Treatment Plant is located near the outlet of Lower Gar on 28th Street in Milford.  The wastewater treatment plant takes wastewater from Orleans, Spirit Lake, Okoboji, Arnolds Park, West Okoboji Wahpeton, Milford and unicorporated areas around the Iowa Great Lakes.  The plant treats about 2.5 million gallons of wastewater a day the discharges the treated water to Milford Creek.

Support Post for the Solar Panels Being Installed
Off loading the first pallet of Solar Panels 9/10/2020

Notice to Bidders for Project 2018-1, Center Lake Sanitary Sewer Improvements, Phase 1A- Bid Package 4

The full Notice to Bidder for Project 2018-1, Center Lake Sanitary Sewer Improvements, Phase 1A-Bid Package 4 can be found at the line below.  The work in general includes the following:

The project consists of furnishing all labor, materials, and equipment necessary to complete installation of approximately 722 linear feet of 16-inch diameter and 210 linear fee of 18-inch diameter AWWA C900 DR 18 polyvinyl chloride (PVC) gravity sanitary sewer by open trench construction; abandonment/removal of 3 concrete manholes; installation of 3 pre-cast concrete manholes, and reconnection of sanitary sewer services.  Additionally, the project contains excavation, dewatering, backfill, roadway (asphalt concrete) removal and replacement, utility relocation and adjustment (if needed), and sitework together with related subsidiary and incidental work in accordance with the plans and specifications.

Notice to Bidders for Project 2018-1, Center Lake Sanitary Sewer Improvements, Phase 1A- Bid Package 4

 

Notice to Bidders East Lake Interceptor Relocation Project

The full Notice to Bidders for the East Lake Interceptor Project is found at the link below. The work in general includes the following:

A sewer interceptor relocation within Orr’s Camp Winakawin RV Park and a short sewer replacement east of Upper Gar Lake and south of Linden Dr, both in Dickinson County, IA.  It consists of furnishing all labor, materials, and equipment necessary to complete the installation, via open cut construction of approximately 500 LF of 8-inch diameter, 350 LF of 10-inch diameter, 900 LF of 24-inch diameter, and 650 LF AWWA of 30-inch diameter, all C900 DR 18 polyvinly chloride (PVC) gravity sanitary sewer (East Lake Interceptor) and new manholes.  It also includes several 4-inch diameter servcies to be installed along with 8-inch where RV stalls are present; abandonment of 24-inch diameter gravity sewer; abandonment of concrete manholes; service stub outs at manholes; and reconnection of existing sanitary sewer services.  Additionally, the project is anticipated to involve excavation, dewatering, backfill, roadway/trail removal and replacement (gravel and concrete), utility relocation and adjustment, and sitework, together with related subsidiary and incidental work in accordance with the plans and specifications.

Notice to Bidders East Lake Interceptor Relocation Project 2020-2

South Center Lake Presentation and Flag Delivery

The power point presentation that was presented online on April 1, 2020 is now uploaded on to the Sanitary District website.  The location click on the South Center Lake Page link on the below.

Flag for location of your septic tanks have were delivered today.  An HR Green representative will be back through the area next week to see if everyone was able to find their flag.  It should be a green colored flag and should be close to the front door.

 

South Center Lake Project Page

South Center Lake Project

The Iowa Great Lakes Sanitary District is starting the design phase of the South Center Lake Project.  This project will be extending the public sewer to help improve water quality on Center Lake.  The project will consist of installing a gravity sewer, a new lift station and a sewer force main.  The project is projected to start in the fall of 2020 with the lift station.

Click on the following link to go to the page for the additional information:  South Center Lake Sewer Project