CAPITAL IMPROVEMENTS 2030

This is a list of the planned 2030 capital improvements project.  There is currently $11,000,000 budgeted for this year.

SOUTH MILFORD LIFT STATION

This will be to replace the Sanitary District's lift station on the south end of town just west of Highway 71.  This lift station will be replaced with and will go from submersible pumps to non-submersible pumps.  The cost of this project is estimated to be $3,000,000.

PLANT IMPROVEMENTS

This is additional funds for the any plant improvements that may be needed.  Funds of $2,000,000 will be budgeted for these possible improvements.

POSSIBLE REPLACEMENT OF 1939 CLAY LINES

The 1930's sewer lines will be getting close to being 100 years old and need to be evaluated for possible replacement.  This would need to be completed is sections and could cost over $5,000,000.