2030 Capital Improvement Projects

The estimated cost for 2030 improvement projects is estimated to be around $11,000,000

South Milford Lift Station

This will replace the Sanitary District's lift station on the south end of town, just west of Highway 71. The lift station will be replaced with non-submersible pumps. The cost of this project is estimated to be $3,000,000.

Plant improvement

This is additional funding for any plant improvements that may be needed.  $2,000,000 will be budgeted for these possible improvements.

Possible replacement of 1939 clay lines

The 1930s sewer lines will be getting close to 100 years old and must be evaluated for possible replacement.  This would need to be completed in sections and could cost over $5,000,000.