2029 Capital Improvement Projects

The estimated cost for 2029 improvement projects is estimated to be around $5,000,000

Loch Knolls sewer replacement

This project will replace the gravity sewer going to the Loch Knolls lift station. It will impact the area from Charlstrom's Beach to Parks Marina. The project will include about 4,200 feet of 8-inch sewer (possibly increasing to 10 inches), 4,000 feet of force main sewer, and 23 manholes. The estimated project cost is $4,000,000.

Plant improvement

These are funds that are set aside for possible plant improvements.  The amount of $2,000,000 has been set aside for improvements.