Haywards Bay Lift Station and Force Main Project
The Iowa Great Lakes Sanitary District has started a project to create more capacity for the center core system of the Sanitary District’s collection system. This project includes a new lift station located north of the intersection of Lakeshore Drive and 220th Avenue. This lift station will replace the 1930s-era lift station within 120 feet of West Okoboji Lake on Alexander Street in the City of Okoboji. The new lift station will pump water south down Lakeshore Drive, then east on Nature Center Road (formerly County Home Road) to the Nature Center, where the line will then turn south and go to Brooks Golf Course. At Brooks Golf Course, the new sewer force main will go under the golf course and towards an area behind Liberty National Bank. The line will then go south to Brooks Park Drive to the Highway 71 Right-of-Way, then south in front of Amercinn and Arrowwood Resort,, connecting with the existing public sewer system.
The lift station project has started and is contracted to be substantially completed by September 25, 2020.
The sewer pipe installation is broken up into four bid packages.
Bid Package #1 is the open trench installation of a sewer from the south parking lot of Arrowwood Resort north to AmericInn. The line will go west approximately 550 feet, then north about another 900 feet, and stop. This will be an all-gravity sewer. Bid Package #1 is to be substantially completed by May 1, 2020.
Bid Package #2 is the directional boring installation of the force main sewer in two areas. The first directional boring will start in an area behind Liberty National Bank and go under Brooks Golf Course to the northwest and into an area south of the Nature Center. The pipe will then go up to Nature Center Road on the west side of the current Nature Center Driveway. The second directional boring area will be from the intersection of Nature Center Road and Lakeshore Drive, going north to the new lift station site. The pipe will stay on the east side of Lakeshore Drive. Bid Package #2 is to be substantially completed by May 8, 2020.
Bid Package #3 is the open trench installation of a force main sewer to connect the two-direction drilling sites. A new gravity sewer line will be installed from Lakeshore Drive east to the Nature Center on Nature Center Road. This project will be substantially completed by May 29, 2020.
Bid Package #4 involves the open trench installation of a new gravity sewer from the old lift station on Alexander Street to the new lift station site. This work will start in the early fall of 2020.