Center Lake improvements phase 1B
Center Lake Improvement Phase 1B was broken up into four Bid Packages. This project phase involved installing the new force main and gravity sewer from the new Hayward Bay Lift Station and the gravity sewer east of Lakeshore Drive to the Nature Center on Nature Center Road.
Bid Package 1
This phase of the project started near Highway 71 in the Arrowwood Parking lot. It involved installing gravity sewers and manholes from the Center Core sewer line north to the eastern edge of Brooks Golf Course. Hulstein Construction was awarded the contract, which cost $2,402,757.48.
Bid Package 2
This project phase was to directional bore in a fused force main sewer pipe in two areas. CES Industrial fused the 18-inch force main, and EBI Drilling Services installed the pipe. The first pipe was installed across Brooks Golf Course and west of the Dickinson County Nature Center. The second site was from the intersection of Lakeshore Drive and Nature Center Road, going north to the new lift station. The contract was awarded to Hulstein Construction with a total project cost of $831,530.20
Bid Package 3
This project phase involved installing the force main and gravity sewer along Nature Center Road from Lakeshore Drive to the Dickinson County Nature Center. This allowed the Nature Center to have gravity sanitary sewer and remove the old lift station for that building. Crow River Construction was awarded the contract, which cost $2,057,450.43.
Bid Package 4
This was the final phase of the project, and it was to connect the gravity sewer from the 1930s lift station to the new lift station for Haywards Bay. This project installed a gravity sewer between the two lift stations and then grouted the old Haywards Bay lift station force main with grout. The contract was awarded to Geislinger & Sons Inc., and the total project cost was $1,151,737.62.
East Lake interceptor project
This project was to improve the East Lake Interceptor installed in the late 1970s and early 1980s. It worked in two areas: the first was south of Bridges Bay Resort, and the second was in Oar's Campground. The project added a slope to the pipe to increase capacity in the north construction area. The pipe route was changed in the south construction area, and the pipe slope was improved to create more capacity. The contract was awarded to H&W Contracting, and the final project cost was $1,629,533.69.
Wastewater treatment plant solar project
This project was to offset continually increasing power costs. Ziegler Energy Solutions LLC submitted the proposal to install a solar panel system for the plant. To learn more about the solar project or to see live power generation and power demand, check the Solar Project Link.