Okoboji Harbor Schedule

Updated December 3, 2015

SECTION A PRELIMINARY CONSTRUCTION SCHEDULE

Click the link to access the Section A preliminary construction schedule.  The project Contractor, Lessard Contracting Inc., is anticipating starting construction of the project the week of July 13th or July 20th.  The preliminary construction schedule is setup with construction segments numbered 1 thru 10.  Lessard Contracting will be starting at construction segment 1 and working their way in numerical order to construction segment 10.  Lessard Contracting anticipates that each construction segment will take roughly 2 to 3 weeks to complete.  This time frame is rough and will be revised and update once construction starts and Lessard Contracting has a more accurate understanding of how long the work will take to complete.  Update construction schedules will be posted monthly.

PRIVATE SEWER SERVICE INSPECTIONS

  • State Date – April 6, 2015
  • End Date – April 21, 2015

SECTION A

  • Exploratory Work – June 22 – 26, 2015
  • Significant Work Started – July 6, 2015
  • End Date – December 24, 2015

SECTION B

  • Work to Start – January 11, 2016
    • Main line work done around January 22, 2016.
    • Lateral line work start around January 22, 2016
  • Work to end -February 12, 2016

SECTION C

  •  Estimated Start Date –
  • Estimated End Date –